PRICE, Judge.
This appeal was taken by the plaintiff-landowner from the judgment of the trial court holding that the defendant-contractor was not liable in damages for his failure to complete a land clearing contract because of excessive rainfall.
The factual background giving rise to this litigation is summarized by the trial judge in his reasons for judgment as follows: