The plaintiff and the Health and Mental Hygiene Facilities Improvement Corporation (now the defendant) entered into a contract on September 30, 1971 whereby the plaintiff agreed to perform certain construction for a certain sum of money. The contract contained the customary provision whereby acceptance of the last payment on the contract, except retainage, by the plaintiff would be a complete release of defendant "from all claim and liability * * * for anything done or furnished...