Petitioner-appellant American Airlines, Inc., seeks to stay arbitration sought under the broad arbitration clause contained in the usual American Institute of Architects "General Conditions" annexed to the construction contract between the parties. The procedure provided calls for submission of the claim to the job's architect in the first instance, actual demand for arbitration not to be made until the earlier happening of either the architect's determination of the claim...