SCHWARTZ, ALAN, R., Associate Judge.
The plaintiff-appellee, a materialman not in privity with the general contractor, secured a summary judgment for the full amount of his claim, against the surety on a performance bond posted by the general contractor under F.S. § 713.23, notwithstanding the plaintiff's admitted failure to give timely notice to the owner as required by F.S. § 713.06(2). We reverse.
The statutory provision in question, F.S. §...