PER CURIAM.
Defendant appeals by leave granted from denial of its motion for accelerated judgment by the trial court. The Detroit Edison Company purchased from defendant General Electric a transformer which was shipped February 21, 1968 and arrived at the buyer's place of business March 4, 1968. Damage to the transformer was discovered on April 13, 1968, after it had been installed by defendant W.D. Gale, Inc., a contractor. Suit was begun March 13, 1972, by Centennial...