MATTER OF OPARK CONSTR. CORP.


42 N.Y.2d 1025 (1977)

In the Matter of the Arbitration between Opark Construction Corporation, Appellant, and Eureka Constructors, Inc., Respondent.

Court of Appeals of the State of New York.

Decided October 4, 1977.


Attorney(s) appearing for the Case

Alfred J. Swan for appellant.

Jerrold Morgulas for respondent.

Chief Judge BREITEL and Judges JASEN, GABRIELLI, JONES, WACHTLER, FUCHSBERG and COOKE concur in memorandum.


MEMORANDUM.

The order of the Appellate Division should be affirmed, with costs.

The contract negotiated by the parties provided specifically for arbitration of any dispute arising in connection with the delay claim here asserted. Although the parties subsequently entered into a settlement agreement, its effect upon the delay claim is in dispute. Since a valid provision to arbitrate exists, the issue of whether the...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases