BARNES v. KESLER & SONS CONSTRUCTION COMPANY

No. 14204.

549 P.2d 441 (1976)

R. Lloyd BARNES, dba Electrical Construction Company, Plaintiff and Appellant, v. KESLER & SONS CONSTRUCTION COMPANY, a Utah Corporation, et al., Defendants and Respondents.

Supreme Court of Utah.

April 28, 1976.


Attorney(s) appearing for the Case

David A. Goodwill, of Foster, Cutler, Price & Goodwill, Salt Lake City, for plaintiff-appellant.

Grant S. Kesler, Salt Lake City, for defendants-respondents.


ELLETT, Justice:

Kesler had a contract to install a sprinkling system including some underground electrical wiring on a golf course.

Barnes had a subcontract from Kesler to install the electrical wiring system at an agreed price of $3848. At the date of trial, Barnes had been paid $2,078.95 leaving an unpaid amount of $1,769.05.

The evidence showed that some of the electrical wires were severed by Kesler with its digging machinery and Barnes was required...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases