STOLZ, Judge.
Appellants (contractors) sued the appellee (Highway Department) to recover claims for (1) retainage of $5,981.66 plus interest, (2) payment of $204,869.37 for "removal of muck and sanitary landfill" to extra depths, plus interest, and (3) payment of $1,000,064.50 for "overhaul on excavation" plus interest, arising out of a highway construction contract. The highway department admitted that the $5,981.66 retainage was owed, and paid the sum into the registry...