NEWTON, Justice.
This is an action to recover on a construction contract for the erection of a duplex. Defendant failed and refused to make the final payment due on the contract. The claim was assigned to plaintiff. Defendant claimed a setoff for defective construction. On trial to the court, judgment was entered for defendant. We affirm the judgment of the District Court.
The contract provided for the furnishing of all labor and materials by the contractor...