CONSOLIDATED EDISON COMPANY v. F. P. C.

Nos. 73-1999, 73-2017, 74-1150, 74-1200.

518 F.2d 448 (1975)

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC., Petitioner, v. FEDERAL POWER COMMISSION, Respondent, Brick Institute of America et al., Intervenors. STATE OF NORTH CAROLINA and North Carolina Utilities Commission, Petitioners, v. FEDERAL POWER COMMISSION, Respondent, Piedmont Natural Gas Co., Inc., et al., Intervenors. ALABAMA GAS CORPORATION, Petitioner, v. FEDERAL POWER COMMISSION, Respondent, Southeast Alabama Gas District et al., Intervenors. ATLANTA GAS LIGHT COMPANY, Petitioner, v. FEDERAL POWER COMMISSION, Respondent, South Carolina Electric & Gas Company et al., Intervenors.

United States Court of Appeals, District of Columbia Circuit.

July 25, 1975.


ORDER

PER CURIAM.

On consideration of the petition for rehearing and clarification, filed by North Carolina and North Carolina Utilities Commission, petitioners in No. 73-2017, it is

Hereby ordered by the Court that the petition for clarification is granted, and the petition for rehearing is denied, for the reasons herein indicated.1

Our opinion, written at a time when the practical effects of the challenged FPC...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases