ORDER
The motion for injunction pending appeal is denied except as follows: No additional new clearing work shall be done on the power line corridor so that the timber, shrubs, etc. on the remaining approximately nine miles of planned corridor will not be cut or affected until the regular panel hearing this case orders otherwise.
ELY, Circuit Judge (dissenting):
The National Environmental Policy Act, 42 U.S.C. § 4321 et seq., became effective...