On December 24, 1964 the plaintiff entered into a contract with the village to install sewer lines. The plaintiff's construction was to commence within 10 days thereafter. However, the village had not then obtained certain necessary easements and permits. The trial court has found that, as a result, the plaintiff was required to work in areas where additional expenses were incurred due to the presence of deeper frost in the ground. The failure of the defendant to obtain the...
Let's get started
Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.
- Updated daily.
- Uncompromising quality.
- Complete, Accurate, Current.