The question we are to decide on this appeal is whether the Court of Claims properly granted defendants' motion for summary judgment in regard to plaintiffs' claim for damages of $18,920.36 arising out of delay in the scheduled date for the start of construction of a bridge over the Clinton River. Summary judgment was made under GCR 1963, 117.2(1) on the ground that plaintiffs failed to state a claim upon which relief could be granted.
On March 7...