PER CURIAM.
Appeals from a judgment which ordered interest on the judgment from a date earlier than the date of the verdict. The suit was to recover the balance allegedly due for the removal of gravel from plaintiff's gravel pit. The jury found for plaintiff against the subcontractor, Fischer Construction Co., Inc., and Fidelity and Deposit Company of Maryland, its bonding company, and the prime contractor, Husting and Engstrom, Inc., and United States Fidelity and...