OPINION
JACOBSON, Chief Judge of Division One.
The issues raised by this appeal and cross-appeal are whether a contractor is entitled to pre-judgment interest on the amount found due under a cost-plus with a maximum construction contract and whether the trial court's factual determinations are supported by the evidence.
This protracted litigation originated out of a contract entered into on December 27, 1963 between the plaintiff-appellant Homes &...