Judgment modified, on the law and the facts, by reducing the principal award to plaintiff from $33,734.93 to $13,311.73 and accordingly reducing the amount allowed as interest and the total amount of the judgment. As so modified, judgment affirmed, without costs.
In our opinion there is no basis for a recovery by plaintiff, a subcontractor for the excavation and installation of underground utilities, against appellant, the prime plumbing contractor, from which plaintiff...