This is a motion by third-party defendant Westinghouse Electric Corp. for summary judgment dismissing the third-party complaint. In the primary action, plaintiff Architectural Aluminum Corporation alleges that it contracted with defendant, Macarr, Inc. for the installation of a rectifier to be in working order on January 2, 1969. The complaint alleges that the unit was not in working order...