SCHOOL DISTRICT NO. 91, BONNEVILLE COUNTY v. TAYSOM

No. 10837.

495 P.2d 5 (1972)

94 Idaho 599

SCHOOL DISTRICT NO. 91, BONNEVILLE COUNTY, State of Idaho, for the Use and Benefit of IDAHO CONCRETE PRODUCTS, INC., an Idaho corporation, Plaintiff-Respondent, v. Eli TAYSOM, an individual dba Taysom Construction Company, et al., Defendants-Appellants.

Supreme Court of Idaho.

March 21, 1972.


Attorney(s) appearing for the Case

Whittier & McDougall, Pocatello, for defendants-appellants.

Holden, Holden, Kidwell, Hahn & Crapo, Idaho Falls, for plaintiffs-respondents.


McQUADE, Chief Justice.

In 1967 Eli Taysom, doing business as Taysom Construction Company (contractor) was awarded a contract to build Skyline High School for School District No. 91 in Bonneville County. He duly executed a payment bond with United Pacific Insurance Co. as surety, and sub-contracted with Levi Gifford, doing business as Gifford & Driesel Masonry Construction (sub-contractor), to perform the masonry work on the new school. The sub-contractor worked...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases