Judgment reversed and cause remanded.
Mr. JUSTICE McNAMARA delivered the opinion of the court:
The primary issue on appeal is whether a contractor, in an action to enforce a mechanic's lien against a property owner, establishes the prima facie evidence of the amount due under the lien statute by introduction into evidence of the contract price for the work agreed to with a third-party lessee.
The action, to foreclose a mechanic's lien for improvements...