Judgment affirmed.
Mr. JUSTICE THOMAS J. MORAN delivered the opinion of the court:
Plaintiff, a general contractor, brought an action for extra work performed and for construction of a pool and cabana which were not included in the contract price of the home built for defendants. Defendants appeal from a jury verdict of $12,000 in favor of plaintiff.
On appeal, defendants contend that: 1) plaintiff cannot recover for orally requested extras because...