MEMORANDUM DECISION
BAILEY BROWN, Chief Judge.
This is an action to enjoin the Secretary of Transportation from releasing federal funds to the Highway Department of the State of Tennessee for construction of a segment of an interstate highway through Overton Park in Memphis. This Court granted summary judgment for defendants. 309 F.Supp. 1189 (1970). The Court of Appeals for the Sixth Circuit affirmed. 432 F.2d 1307 (1970). The Supreme Court reversed and remanded for a plenary review of Secretary Volpe's approval of the release of federal funds for this project in November, 1969. 401 U.S. 402, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971). This hearing has since been held. The background of this litigation is fully set out in those opinions.
In its opinion, the Supreme Court gave a narrow interpretation to the requirement of § 4(f) of the Department of Transportation Act of 1966 (49 U.S.C.A. § 1653(f))
Having so interpreted § 4(f) of the Act, the Supreme Court further held (401 U.S. at 413, 91 S.Ct. 814) that, since there is "law to apply" by the Secretary, his determinations are reviewable under the Administrative Procedure Act (5 U.S.C.A. § 701 et seq.) and proceeded to determine the standard for review. It concluded that the determination is not to be reviewed de novo and not even to be subjected to the "substantial evidence" standard. 401 U.S. 414-415, 91 S.Ct. 814. It held, however, that, while the Secretary's determination is entitled to a presumption of regularity, this court, in reviewing his determination, must "engage in a substantial inquiry . . . [which is] thorough, probing, in-depth . . ." (401 U.S. at 415, 91 S.Ct. at 823), and the opinion then explicitly spells out the standard for our review as follows:
Although the opinion of the Supreme Court, as has been seen, admonished us to conduct a thorough plenary hearing and explicitly set out the determinations that we are to make, the opinion adds this caveat: "Although this inquiry into the facts is to be searching and careful, the ultimate standard of review is a narrow one. The court is not empowered to substitute its judgment for that of the agency." 401 U.S. at 416, 91 S.Ct. at 824.
The Supreme Court held that, contrary to the contention of plaintiffs, the failure of the Secretary to make formal findings and state his reason for his approval does not require a remand to him. 401 U.S. at 417-419, 91 S.Ct. 814. The Court also held, however, that it was improper to base our review, as we did when we granted summary judgment, on the litigation affidavits with exhibits and that the basis for review should be the "`whole record' compiled by the agency: the basis for review required by § 706 of the Administrative Procedure Act." 401 U.S. at 419, 91 S.Ct. at 825.
Thus the Court held that the case must be remanded to this court for plenary review of the Secretary's decision, "[the] review . . . to be based on the full administrative record that was before the Secretary at the time he made his decision." 401 U.S. at 420, 91 S.Ct. at 825. It pointed out, however, that the "bare record may not disclose the factors that were considered or the Secretary's construction of the evidence . . .," and that therefore testimony of the persons involved in making the decision might be necessary. 401 U.S. at 420, 91 S.Ct. at 825. Such inquiry into mental processes, the Court said, should ordinarily be avoided, and where there are formal findings and reasons stated in support thereof at the time the decision is made, there must be clear proof of bad faith or other improper conduct before the mental processes of the agency people may be investigated. The Court pointed out that the Secretary could even later make formal findings that might provide a sufficient explanation of his decision, but such findings would, like the affidavits before the Court on motion for summary judgment, have the aspect of a "post hoc rationalization" which must be reviewed in that light. Lastly the Court said that if the trial court decided that "additional explanation" is
A short while after the decision of the Supreme Court came down on March 2, 1971, we met informally with counsel for the parties to discuss the future course of this case. Counsel for the Secretary indicated that it would require at least six weeks to assemble the administrative record, and that when this was accomplished, it would be filed. (It actually was not filed until July 14, 1971). Counsel for the plaintiffs then stated that they would want to take some discovery depositions after the record was filed. Defendants objected to this, contending that the first inquiry should be to determine whether the Secretary's decision could be reviewed on the bare administrative record alone and that, if so, such discovery would be unnecessary. We concluded, however, and so indicated to counsel, that plaintiffs were at the very least entitled to discovery to determine whether the record as filed was complete. At that time it was not known to counsel whether the Secretary would prepare and file formal findings. We therefore also indicated to the parties, in line with our interpretation of the Supreme Court's opinion, that plaintiffs should be allowed, in taking the discovery, to explore the mental processes of the agency people, including the Secretary, and that we would later decide to what extent such proof would be admissible at the hearing. The Secretary has never prepared and filed formal findings,
At a formal pre-trial conference on September 7, 1971, we ruled that plaintiffs would be entitled to offer expert testimony to evaluate the investigation of alternative routes by the Secretary. We so ruled because we thought expert testimony would be competent as an aid to the court in evaluating the expertise exercised by the Secretary and his associates. We also at that time ruled that plaintiffs could offer expert proof to show that there were in fact feasible and prudent alternative routes. Our theory in so ruling was that, so far as we judicially knew, there could be an obviously feasible and prudent alternative and that if such could be shown, it would undercut the good faith of the administrative investigation, particularly if it in no wise appeared in the administrative record.
We further ruled, at this pretrial conference, that defendants would not be entitled to show the amount of money that would, so to speak, go down the drain with an abandonment of the route through the park. We so ruled because it was dramatically clear at the time of the Secretary's determination in November, 1969 and at the time of the presentation of this case in the Supreme Court that condemnation of land and removal of buildings was almost complete on the park route and yet the opinion of the Court, while recognizing that the cost of alternative routes could properly have been considered, omits this as a proper factor for consideration when the Secretary made the decision. A question that is related to the foregoing one and was not ruled on at the pre-trial conference is the question whether the Secretary, in weighing the community disruption factor in making his determination, could properly consider the fact that the disruption on the park route had already occurred while disruption on another route would be new and additional. We reserved this question at the plenary hearing. On reflection, we are of the opinion that, since these facts were likewise dramatically
The plenary hearing began on September 27 and terminated on November 4, 1971, consuming twenty-five trial days, and 240 exhibits were admitted in evidence. We believe that it can fairly be said that the inquiry was substantial, thorough, probing, in-depth, searching and careful. We have also had the benefit of 287 pages of post-trial briefs.
With respect to the route of the interstate highway through Overton Park, it is one of plaintiffs' contentions that Secretary Volpe, whose November, 1969 determination we are reviewing under the specific direction of the remand decision of the Supreme Court, did not actually consider any alternative routes to the park route for the purpose of making that determination. It is the Secretary's memory that he did, as he states in the affidavit dated July 15, 1971 and in his deposition taken on August 31, 1971. However, we find that, whether or not we consider the affidavit and deposition as a "post hoc rationalization," the evidence is overwhelming that Secretary Volpe did not so consider alternatives. In the first place, it has been the position of Secretary Volpe through counsel in this court that his approval of the park route was unnecessary since it had been approved by Federal Highway Administrator Whitten in 1966 (before § 4(f) was enacted) and, more particularly, since it has been approved by Secretary Boyd, Volpe's predecessor in office, in April, 1968 pursuant to § 4(f). Secondly, the public hearing held by the Federal Highway Administration in Memphis in May, 1969 was, as has been correctly contended by Secretary Volpe in this litigation, only a design hearing and was not also a route hearing. Thirdly, it is without dispute here that in this case the Solicitor General of the United States argued in the Supreme Court that Secretary Volpe's November, 1969 determination was a design approval but not a route approval. Fourthly, J. D. Braman, who was Assistant Secretary of Transportation for Environment and Urban Systems under Volpe, testified that, while he frequently advised with the Secretary on § 4(f) matters, he was never asked to investigate alternatives to the park route and understood that this matter was foreclosed by prior decisions and actions. Oscar Gray, an attorney in the Department whose concern was environmental matters, supported Braman with his testimony. Fifthly, there is not a document in the administrative record that indicates that Secretary Volpe considered and ruled out route alternatives. Sixthly, even Secretary Volpe's announcement of his decision on November 5, 1969 (which is in the form of a press release) indicates on its face that the Secretary was merely reaffirming a prior route determination and that he had only considered design alternatives. This press release states in part:
Thus we conclude that, because of approval by Secretary Boyd
Since we have concluded that Secretary Volpe did not determine at all that there was no "feasible and prudent" alternative as, the Supreme Court's opinion makes clear, he was required to do, we would for this reason alone have to remand this matter to him to make such determination. There is, however, another reason why this matter must be remanded. This reason is that, even if it could be said that Secretary Volpe made a determination that there was no "feasible and prudent" alternative to the park route, it is clear that he did not give these words the interpretation that the Supreme Court did and that therefore he did not apply the correct legal standard. The Secretary's position is that he applied a standard that was the same or substantially the same as that laid down by the Supreme Court.
In this connection, it should first be pointed out that the Supreme Court's interpretation of § 4(f) is contrary to what the Department of Transportation and its Secretary must have expected it to be. As we have already indicated, the Court has by its interpretation narrowly limited the choices of the Secretary. In doing so, as we have also already indicated, the Court gave no effect to the proviso in § 4(f) having to do with decisions by local officials. The Court further, in so construing the provision, expressly declined to accept the Secretary's argument that the requirement in § 4(f) that the alternative be a "prudent" one allowed him to balance competing interests and to weigh the detriment to the park against the disadvantages of avoiding the park and then determine whether, on balance, the alternative route was a "prudent" one. "[N]o such wide-ranging endeavor was intended." 401 U.S. at 411, 91 S.Ct. at 821. In so interpreting § 4(f), the Court "felt it necessary to focus only on the language of the statutes to determine legislative intent." The Supreme Court, 1970 Term, 85 Harv.L.Rev. 315 (1971) at 325. It gave little, if any, weight to Congressional Committee reports. Id., at 325, footnote 54. And it did not deal with the complex policy issues in construing § 4(f). Id., at 324.
There are other indications in the record that Secretary Volpe did not apply the correct standard. In his deposition, Volpe did not indicate that he had understood at the time he made the decision in November, 1969, that § 4(f) had the meaning that the Supreme Court has given it. In his affidavit, the Secretary does say that, applying the correct standard as laid down in the Supreme Court's decision, he would have concluded that there was no feasible and prudent alternative to the park route, but he does not say that he applied such a standard when he made the decision. Moreover, the Secretary's position in this court when this case was first before us and his position in the Supreme Court was that he was indeed entitled, under § 4(f), to balance the detriment to the park against the disadvantages of a route that would avoid the park. There is nothing in the administrative record to indicate that anyone in the Department of Transportation in 1969 had any notion that § 4(f) so narrowly constricted the Secretary's options. The
Thus we must reach the conclusion that Secretary Volpe, if he did consider alternatives to the park route, must have, however understandably, applied an incorrect standard.
Defendants contend that, even if the Secretary applied an incorrect standard in determining that there was no feasible and prudent alternative, this matter need not for this reason be remanded to him if his decision is supportable, applying the correct standard, by the administrative record. In this connection, defendants point out that, in its opinion, the Court said that this court "[M]ust consider whether the Secretary properly construed his authority . . .." (Emphasis added.) 401 U.S. at 416, 91 S.Ct. at 823. Since we need only "consider" whether the Secretary correctly construed his authority, defendants argue, a misconstruction of his authority is not necessarily fatal to the validity of his decision. However, as we read this part of the Court's opinion in its entirety, the Secretary cannot be held to have acted within the scope of his authority if he misconstrued his authority at the time he made the determination, for otherwise we would have been directed to determine only whether, applying the correct standard, the Secretary's determination is supportable by the record. This is not only implicitly, if not explicitly, clear from the Court's opinion, but it is also implicit in the statutory scheme that the Secretary, exercising expertise, make the determination whether there is a "feasible and prudent" alternative. If this reviewing court refused to remand, even though the Secretary had applied an incorrect standard, simply because, on the record, he could have, applying the correct standard, within reason approved the park route, we would thereby substitute our judgment for his in applying the statute. We would agree that if the record that was before the Secretary were such that, even applying the correct standard, he could not within reason have determined that there was a "feasible and prudent" alternative, it might well be that the application of an incorrect standard would be harmless error, but this is not the case here. On the contrary, for reasons stated, we are of the opinion that on the record the Secretary could properly have determined either that there was or that there was not a feasible and prudent alternative.
At the plenary hearing, plaintiffs took the position that the alternative routes immediately north and immediately south of Overton Park were not only not "feasible and prudent" alternatives but that, on the contrary, they were put forward by the Highway Department of the State of Tennessee to undermine opposition to the route through the park. Thus plaintiffs contended that the disruption and cost involved in those two routes was so great that they were not suggested for consideration in good faith and constituted a fraud.
The "feasible and prudent" alternative route, and the only one, supported by plaintiffs at the plenary hearing is a
The administrative record reflects that by 1955, as a result of studies by the firm of Harland Bartholomew and Associates, which had done the planning for Memphis for many years, a general plan was evolved which included a circumferential expressway and two east-west expressways, one of the latter of which was the park route and the other of which would generally parallel the park route to the south. These two east-west expressways were so located, according to the planners, to give the maximum service and to meet the long-term needs of the City, and thereafter other street planning was done and carried out on the assumption that these expressways would be constructed in such east-west locations. This work is part of the administrative record. About 1958, the possibility of altering the park route to make use of the L & N right-of-way was considered. Apparently, it was thought that, due to a merger of the L & N and its subsidiary railroad, the N C & St. L, the L & N right-of-way would no longer be used and could be purchased. In any event, at the request of the City, Harland Bartholomew & Associates studied this possibility, including the use of the open area alongside Cypress Creek, and rejected it, primarily, it appears, because the expressway along that route would not be properly located to give the desired service, would add mileage to the thousands using the expressway forever, and would not fit the plan for the development of the other expressways and streets in the City. As stated, this is also in the administrative record.
As heretofore indicated, it is our view that, as of November, 1969, when Secretary Volpe made his determination, the administrative record was such that, based thereon, he could have reasonably believed that the use of any route except the park route was not consistent with "sound engineering" and that it would involve "truly unusual factors." We also find that he could have reasonably believed the contrary. It is further our view that the Secretary, based upon the relevant factors and weighing them as required, could have, without being arbitrary or capricious, determined that the use of any route except the park route was not consistent with "sound engineering" and that it would involve "truly unusual factors" and that, in so deciding, would not be guilty of a clear error of judgment. We also find that he could have determined and decided to the contrary, without his decisions being arbitrary or capricious and without committing a clear error of judgment.
In stating our bases for the foregoing findings, it is rather difficult to distinguish because those facts that appear from the administrative record and those facts that were added to the record at
Now the plenary hearing developed additional facts which would even more clearly make a decision against the L & N route within reason and not arbitrary or capricious. It appears that the L & N railroad has not changed its operations and is still making substantial use of this right-of-way both in switching cars in its nearby freight yard and in serving industries. Assuming this line of railroad could be condemned by the United States, as contended by plaintiffs, for this purpose,
The remand decision of the Supreme Court also requires that we review the
We believe that the record shows that Secretary Volpe did consider all design alternatives and that in doing so he applied the correct standard, that is, that all that it is reasonably possible to do must be done to minimize harm to the park. We further conclude that, based on the administrative record, hereinafter summarized, the Secretary could have reasonably believed that the design he approved constituted all that was reasonably possible to minimize harm to the park and that, basing his decision on the relevant factors and weighing them in the light of the requirement that all reasonably possible be done to protect the park, his decision that the design met this test was not arbitrary or capricious or a clear error of judgment. It will therefore not be necessary for the Secretary again to consider the design approval.
The Secretary decided against a cut-and-cover tunnel, which would cost an additional 50 million dollars, decided against depressing the expressway throughout its length across the park, and decided against placing the expressway on the north edge of the park. He decided in favor of depressing the expressway except at the point it crosses Lick Creek, and he decided in favor of changing the design of but placing part of the East Parkway interchange in the park. From the record it appears that the Secretary did consider and within reason could find the following facts. The trees and other vegetation would not be preserved with such a cut-and-cover tunnel. Both the tunnel and completely depressing the expressway would create substantial drainage problems and flooding danger both on the expressway and in the park. In the case of the tunnel, there would be, in view of its length, great ventilating and lighting problems, the vehicle gases would be discharged in concentrated form into the park, and the effect of such a deep excavation on the surrounding wooded areas is uncertain but possibly quite harmful. The effect of the expressway, as presently designed, on the nearby zoo would not be substantial, this being supported by a study by experts. To remove the East Parkway interchange completely from the park would cause severe traffic problems on that main artery and would cause the interchange to be too close to North Parkway. The only advantage in placing the expressway on the north edge of the park is that, so placed, it would not divide the park and would allow the zoo to expand to the south. However, there would be great disadvantages: it would not make use of the present bus route through the park, would require removal of some of the existing zoo buildings, and would place the expressway contiguous to a main traffic artery (North Parkway), which would create interchange problems. Moreover, so placing the expressway would not decrease the noise or air pollution problem, if any, for the zoo, and the zoo has ample room to expand with the expressway built in its contemplated location.
Plaintiffs' proof at the hearing concerning the design supported their proffered alternatives, but did not, as we
In May and June, 1971, plaintiffs sought to amend their complaint to add the claim that Secretary Volpe had failed to comply with the National Environmental Policy Act, 42 U.S.C.A. § 4321 et seq. (NEPA), and that such was necessary before he could effectively approve construction contracts let after the effective date of that Act. Upon objection by defendants, we denied such motion to amend on the ground that NEPA is not applicable here because of undisputed reliance on the approval of the park route prior to Secretary Volpe's approval in November, 1969 and because of reliance on his approval prior to the effective date of NEPA. Named Individual Members etc. v. Texas Highway Department, 446 F.2d 1013 (5th Cir. 1971).
A few days before the plenary hearing plaintiffs, without objection, by amendment to the complaint added some additional contentions. The defendants attack the standing of plaintiffs to make these claims, but we assume here that they do have standing in legal contemplation.
One of these contentions is that the Secretary failed to comply with the provision contained in 23 U.S.C.A. § 134.
Another contention is that the Secretary has failed to comply with the provision contained in 23 U.S.C.A. § 109 (a).
Lastly, plaintiffs contend that the Secretary has not complied with the provision contained in § 109(b).
We conclude, then, that this case must be remanded to the Secretary of Transportation, but only for the purpose of making a route determination in compliance with § 4(f) of the Department of Transportation Act of 1966 as that provision has been construed by the Supreme Court. We further conclude that plaintiffs are entitled to injunctive relief if such appears necessary. In this connection, we are advised by counsel that there is presently no restraining or injunctive order in effect but that defendants have been conducting themselves as if there were such an order in effect.
A judgment will be prepared for entry.
FootNotes
There is an identical provision in § 138 of the Federal-Aid Highway Act of 1968, 23 U.S.C.A. § 138. Hereinafter we will refer only to § 4(f).
Comment
User Comments