HOWARD-GREEN ELEC. CO. v. CHANEY & JAMES CONST. CO.

No. 7110SC458.

182 S.E.2d 601 (1971)

12 N.C. App. 63

HOWARD-GREEN ELECTRICAL COMPANY, Inc. v. CHANEY & JAMES CONSTRUCTION CO., Inc., et al.

Court of Appeals of North Carolina.

August 4, 1971.


Attorney(s) appearing for the Case

Purrington & Purrington by A. L. Purrington, Jr., Raleigh, for plaintiff appellee.

Poyner, Geraghty, Hartsfield & Townsend by Marvin D. Musselwhite, Jr., Raleigh, for defendants appellants.


PARKER, Judge.

Defendant Construction Co. acknowledges that it owes plaintiff a balance of $13,430.45 on account of plaintiff's completed performance under the subcontract for the electrical work, and the sole dispute between the parties is whether that balance is presently due and payable. The written subcontract between plaintiff and defendant Construction Co. contains the following:

"3. Payments shall be made monthly in accordance with the following procedure...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases