Judgment unanimously modified on the law and facts in accordance with the Memorandum, and as so modified affirmed, with costs to claimant.
Memorandum: The trial court in awarding damages for the total taking of claimant's commercial property properly decided that it was a specialty and based its award upon an appraisal of cost less depreciation. The court erred, however, in disallowing cost items of a performance bond, architect's fee, building permit, legal fee and...