On November 5, 1964, claimant entered into a contract with the State of New York for construction in the City of Troy of the Hoosick Street Arterial Highway. The work under the contract was completed and accepted on October 31, 1966, although the contract originally provided for completion on December 1, 1965. Claimant seeks damages in the