PER CURIAM.
This action arose out of a sub-contract between S. S. Silberblatt, Inc., as prime contractor on a housing project, and Carter Electric Company, a subcontractor. The matter is before this court for the second time on appeal by Carter.
We reversed the initial, unreported trial court ruling that the sub-contract had been abandoned by the parties, holding that the sub-contract had remained in existence throughout the relationship of the parties and...