Plaintiffs Norman and Marcella Good brought this action for breach of contract and recovered a judgment of $2,000 against defendant Marrocco Building Company. Defendant appeals as of right.
The first issue on appeal questions the sufficiency of the evidence establishing the breach of contract. Examination of the transcript shows that sufficient evidence was presented to support the trial court's finding...