DEFURIA, J., June 17, 1970.
By preliminary objections, defendant demurs to plaintiff's amended complaint in trespass.
Plaintiff advances a novel claim.
Plaintiff was the general contractor of a school construction project for a school authority, with a time limit for completion. Defendant was the heating and ventilating subcontractor for the authority.
While we speak of general and subcontractor, more accurately plaintiff contracted with the...