STEAKLEY, Justice.
The problem here is one of accord and satisfaction in the context of a summary judgment. We disagree with the Court of Civil Appeals,
Petitioner, Lenox Jenkins, plaintiff below, a subcontractor, sued Henry C. Beck Company, a corporation, the contractor, for alleged unpaid balances due him in the total sum of $16,855.34. Beck in its answer admitted...