FARRIS, J.
In 1966, the City of Bellevue (hereinafter called the City) determined to install several traffic control installations. No firm schedule was set, the installations to be completed at the discretion of the City.
The plaintiff, National Electrical Contractors Association, Puget Sound Chapter, (hereinafter called the Association) insisted that the various installations could not be done without the City first calling for public bids. This action was...