Judgment unanimously affirmed, with costs.
Memorandum:
When, on August 5, 1965, plaintiff declared its subcontractor Phillips Cooling Tower Company in default and terminated its contract and thereafter treated the materials fabricated by Phillips as Phillips' property it thereby rejected such material and title thereto was thereupon revested in Phillips by operation of law (Uniform Commercial Code, § 2-401, subd. [4]). Title to the material having revested...