HENRIOD, Justice:
Appeal from a judgment on a verdict for Weyher. Affirmed with costs to plaintiff.
Cox, prime contractor on a state road construction job, signed a contract with Weyher, subcontractor, to construct a portion of the facility, which was to be completed by June 30th.
There was evidence that before the Weyher contract Cox had a firm understanding with Western Steel for the latter to furnish and install the steel, which company agreed to...