BALDWIN'S STEEL ERECTION CO. v. CHAMPY CONSTRUCTION CO


353 Mass. 711 (1968)

234 N.E.2d 763

BALDWIN'S STEEL ERECTION CO., INC. vs. CHAMPY CONSTRUCTION COMPANY, INC. & another.

Supreme Judicial Court of Massachusetts, Middlesex.

March 1, 1968.


Attorney(s) appearing for the Case

Salvatore J. Basile for Champy Construction Company, Inc.

Henry M. Polese for the plaintiff.

Present: WILKINS, C.J., SPALDING, WHITTEMORE, CUTTER, & SPIEGEL, JJ.


SPIEGEL, J.

The plaintiff brought this bill in equity under G.L.c. 149, § 29, to establish its right to payment for labor and materials furnished by it in the construction of a school in the town of Andover. The trial judge made "Findings, Rulings and Order for Decree" which he adopted as his "Report of Material Facts." He found "that the defendant, Champy Construction Company, Inc. [Champy], is indebted to the plaintiff in the sum of $5,730.00, which sum represents...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases