PER CURIAM.
Defendant appeals a decree foreclosing a mechanic's lien on a restaurant building. The principal issue on trial was whether the builder proved the cost-plus contract under which he claimed the sums for which he filed his lien. The evidence was sufficient to support all findings in favor of the builder.
The defendant also contends that the lien notice was defective in that it contained an alleged lumping of lienable and nonlienable items. The notice...