This is an action for water damages to a university dormitory under construction in Laramie, Wyoming. The dispute revolved around the question as to whether a mechanical joint in a certain water line constructed by sub-contractor Trautman & Shreve was properly installed. The trial court decided the matter on summary judgment in favor of the principal contractor Mead & Mount after certain interrogatories were answered and certain requests for admissions...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases