PARKER, Chief Justice.
On 27 February 1962, plaintiff and defendant entered into a written contract, whereby plaintiff agreed to build the roadway and structures for 4.37 miles of roadway on relocated U. S. 52 in Forsyth County, according to specifications for Project No. 8.17374, for the sum of $1,580,628.17. Completion date for the project was, as set out in the contract, 1 March 1963, and liquidated damages at the rate of $400 per calendar day were to be assessed...