PER CURIAM.
The sole question presented on this appeal is whether or not the trial court erred in directing verdict in favor of the appellee (herein "PBA") and against appellant (herein "Surety"), surety on a payment bond guaranteeing payment of labor and materialmen by a general contractor, in a suit by the Surety for recovery of $14,306.42 paid out by PBA to the contractor on progress estimates certified correct by its architect at a time when PBA, Surety and the...