HAMILTON, J.
Appellant (plaintiff) a heavy construction contractor, commenced this action against respondent, the State of Washington, seeking to recover added expenses and penalties incurred due to delay in completion of a highway construction contract. Trial was had before the court sitting without a jury. At the conclusion of appellant's case, the trial court granted respondent's motion for an involuntary nonsuit, and thereafter entered findings of fact, conclusions...