Judgment reversed on the law, without costs, and petition denied.
The petitioner was granted an extension of time by the board, expiring on December 15, 1964, to complete construction of a retail store building for which the board had previously issued a permit (Zoning Resolution of the City of New York, §§ 11-321, 11-322). By December 15, 1964 he had completed the piling, footings, foundation and first floor of the building. He sought a second extension...