HALL, Judge.
This is a suit by a sub-contractor against the general contractor and the owner for a balance amounting to $2,404.72 alleged to be due for additional work performed and additional material furnished by the sub-contractor at the request of the defendants. From a judgment rejecting its demand plaintiff appealed.
The case stems from the refusal of the defendant contractor, Farnsworth & Chambers Co., Inc., to pay plaintiff its cost of replacing...