SHERAN, JUSTICE.
The appeal is from an order of the district court denying defendants' motion for judgment notwithstanding the verdict or, in the alternative, a new trial.
The action was instituted by plaintiff to recover progress payments, retained percentages, and damages for breach of contracts for excavation and backfilling, one being dated August 26, and the other September 20, 1960. In response defendant Watson Construction Company