PER CURIAM.
Appellant instituted suit to foreclose a mechanic's lien for labor performed and materials furnished in constructing a dwelling under a contract with appellees. On final hearing a decree was rendered dismissing the complaint. It is from the decree of dismissal that this appeal is taken.
The critical question before the chancellor was whether appellant's claim of lien was filed within ninety days from the date