EDGERTON, Circuit Judge.
Areawide Building Corporation contracted with appellees, the trustees of Mount Joy Baptist Church, to make alterations and additions to the church building, payment to be made in installments as the work progressed. Areawide abandoned the work after several payments had been made. Article 10 of the contract provided: "Should the Contractor neglect to prosecute the work properly, or fail to perform any provision of the contract, the Owner,...