Order entered on December 19, 1960, denying plaintiff's motion for summary judgment in an action to recover the balance allegedly due on a painting subcontract it had entered into with defendant, unanimously affirmed, on the law, with $20 costs and disbursements to defendant.
In support of its position defendant general contractor points to a provision of its painting subcontract with plaintiff under which the latter assumed toward defendant, with respect to the painting...