DRAPER, P.J.
During performance of its contract for grading the site for defendant district's new high school, plaintiff brought this action for a declaration of its rights and for accrued damages. The case was tried without a jury, and plaintiff appeals from judgment in favor of defendant.
Although the contract called for a lump-sum payment for the work, it also provided that "If rock is encountered which cannot be removed by power equipment and which in...