AGEE, J.
Plaintiff sued defendants in the municipal court to foreclose its claim of lien for materials furnished to a plastering contractor and used by him upon defendants' real property. Plaintiff did not give the pre-lien notice required by section 1193 of the Code of Civil Procedure. However, the municipal court held that this requirement was unconstitutional and, after trial of the issues involved, gave judgment in favor of plaintiff.
On appeal, the Appellate...