WILCO CONSTR. CORP. v. PRYWES


14 A.D.2d 929 (1961)

Wilco Construction Corp., Respondent, v. Aron Prywes, Appellant

Appellate Division of the Supreme Court of the State of New York, Second Department.

November 27, 1961


Judgment affirmed, with costs.

Time was not of the essence in the contract in suit. While plaintiff in its complaint failed to allege the facts showing that it was in default on the date set forth in the contract for the passing of title and showing that such default was excusable and worked no harm on defendant, we amend the complaint to conform to the proof in these respects (Civ. Prac. Act, §§ 109, 434; Thorne Neale & Co. v. New York So. Coal Term...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases