Order reversed on the law and the facts, with costs, and application denied.
Findings of fact insofar as they may be inconsistent herewith are reversed, and new findings are made as indicated herein. The subcontractor's claim admittedly became payable on April 5, 1961. Its request for the statement was mailed to the general contractor on May 2, 1961 and received by it on May 4, 1961. Since less than 30 days had expired after the subcontractor's claim became payable...