PER CURIAM.
This is an appeal from a judgment for the plaintiff in a suit brought under the Miller Act, 40 U.S.C.A. § 270b. The only question here is whether the plaintiff gave notice to the prime contractor within the ninety days prescribed by the act. The trial judge made a specific finding that "both the oral and written notice was given by plaintiff * * * to the prime contractor * * * within ninety days from the date on which John T. Evanick & Company...