DANAHER, Circuit Judge.
Appellants, a contractor and its surety, entered into a payment bond running to the District of Columbia on a bridge construction contract. The contractor placed a verbal purchase order with the L & S Lumber Company, Inc. The latter in turn procured the appellee to treat oak pilings with creosote as called for by the specifications in the contract. The contractor paid L & S, but the latter failed to pay a certain balance due the appellee...