PER CURIAM.
The issue here involves a claim for extra work under a government contract for dredging. In appellee's view, the basic contract did not require that he equalize the banks of the channel in a given area being excavated. This, at greater expense to the appellee, the Bureau of Reclamation insisted upon. The Interior Board of Contract Appeals found by a divided vote in favor of the government.
In our judgment, the root of the case is a fact question...